It is vital that you make note of all major documentation utilised in or related to the inspection that is being conducted, not just the title, but the revision status and reference number have to be recorded.
Any documentation on a project has to be issued directly by the client or if the vendor or a different organization supplied it, the client has to approve it. If an approval of such is not evident, it is extremely important that you mark this out and outline this clearly in the inspection report as either an outstanding action or non-conformity on the client.
You should refer within the report to all attendees present during the inspection, who they represent and their role during the inspection.
Reference should be made to any inspection or measuring equipment that is used during the inspection. This might be because the product we are inspecting had to be measured to give us a representative quantifiable value to sentence against a code, specification or standard to assess the items acceptability.